Most problems on elevator projects are not equipment problems. They are building problems.

Shaft dimensions that drifted during construction, a pit that holds water, a power supply that was never provisioned, or a delivery route that cannot take the components. We work to prevent those, which means being involved earlier than suppliers usually are.

What installation includes

StageWhat happens
SurveyAssessment of shaft, structure, pit, headroom, power and access
SpecificationEquipment selection against building constraints and requirements
Builder's work requirementsWritten dimensions, tolerances and provisions issued to your contractors
CoordinationOngoing liaison with civil, electrical, architectural and interior teams
Delivery and site handlingGetting the equipment to the shaft safely
InstallationRails, machine, car, doors, controls and wiring
Testing and commissioningFull-travel testing and verification of safety devices
HandoverDocumentation, familiarisation and the maintenance plan

What the building must provide

Issued in writing at specification stage so your contractors can build to it.

ItemRequirement
ShaftCorrect internal dimensions, plumb and within tolerance for the full travel
PitCorrect depth, waterproofed, drained where required
HeadroomClearance above the top served floor
StructureCapacity for the equipment's static and dynamic loads
Machine spaceWhere the system requires one, with ventilation and access
PowerCorrect supply, protection and earthing at the right point
Lighting and socketsIn pit, shaft and machine space as required
AccessA route capable of taking the largest component

The single most common cause of delay is a shaft that was built to the drawing but drifted out of tolerance in construction, discovered only when installation begins. A dimensional check before equipment delivery avoids it.

Installing in an existing building

Retrofits add constraints: working around occupants and ongoing operations, forming a shaft within existing structure, resolving fixed pit and headroom, managing noise, dust and access routes, and coordinating with building management on timings.

More of the programme is building work than elevator work. Plan accordingly.

Common questions

How early should an elevator supplier be involved?

At design stage, before the shaft is built. Dimensions, pit, headroom and power provision are far cheaper to design in than to correct.

Who does the civil work?

Your contractor, to our written requirements. We coordinate and verify rather than build.

What happens if the shaft is out of tolerance?

It is identified at the pre-delivery dimensional check. Depending on the deviation, it is corrected, or the specification is adjusted — which is why the check happens before equipment arrives.